I have been caculating a service to feed 10 sleeping quater tents with a caculated load of 30 amps. It will be a 208/120 3 phase system, one phase will 13.8 amps X 1.25 17.25 amps. The Scope of work states a 30 amp service for each tent. Will table 220.84 demand factor appilcable, because 4 split AC/heat pump will be installed in each unit. Can anyone give further detail on demand factor for this kind of distribution.