mstrlucky74
Senior Member
- Location
- NJ
Scenario---- Existing riser tap feeding existing disconnect switch which is to remain. We have to run new conductors from load side extg. switch to new panel.
1. Can you safely make the connections for the new load side conductors while the extg. line side are still live so that you don't have to shutdown the riser? It's 277/480v.
Thanks.
1. Can you safely make the connections for the new load side conductors while the extg. line side are still live so that you don't have to shutdown the riser? It's 277/480v.
Thanks.