I am looking at a new job to bid. Went there to scope it out.
There are 2 bldgs on the site: A and B each separately metered.
Bldg A has a 400A Disconnect 480Y/277V Service. So it is 400x277x3/1000 = 332.4 kW
Bldg B has a 100A Disconnect 480Y/277 Service. So it is 100x277x3/1000 = 83.1 kW
The total for Bldg A and B add to: 332.4kW + 83.1 kW = 415.5 kW
Now the utility pole supplying the entire 2 buildings has 3x75 kW pots (clearly marked 75) up on the pole which is only 225 kW.
Why is the supplied total so much less??????
There are 2 bldgs on the site: A and B each separately metered.
Bldg A has a 400A Disconnect 480Y/277V Service. So it is 400x277x3/1000 = 332.4 kW
Bldg B has a 100A Disconnect 480Y/277 Service. So it is 100x277x3/1000 = 83.1 kW
The total for Bldg A and B add to: 332.4kW + 83.1 kW = 415.5 kW
Now the utility pole supplying the entire 2 buildings has 3x75 kW pots (clearly marked 75) up on the pole which is only 225 kW.
Why is the supplied total so much less??????