Hello all... I've got a project that is absolutely absurd... We're doing a 4MWh ESS system for a 200k sqft build in Colorado. The project is spec'd with (2) 1200A utility services (single phase). We also have the ESS system which we can set up as single or three phase. We're considering doing a three phase system for the property, so the question is could you use solar and batteries for three phase power and then use two separate incoming service feeds w 240-208 transformers to create 3 phase power for a property, even though the utility feeds are single phase.
The concern is that with two 1200A services you'd have two hot legs at 600A from each service, combining them would give two 600A legs and a 1200A leg, or unbalanced three phase. Am I thinking about this correct, and would that work within the property even though it's unbalanced? Let me know what y'all think!
The concern is that with two 1200A services you'd have two hot legs at 600A from each service, combining them would give two 600A legs and a 1200A leg, or unbalanced three phase. Am I thinking about this correct, and would that work within the property even though it's unbalanced? Let me know what y'all think!