Alwayslearningelec
Senior Member
- Location
- NJ
- Occupation
- Estimator
Unique situation here.
Looking at a job that has 9 phases
Each phase has work on two floors.
The overall job schedule is 3 years.
The area of work on each floor is about 2k sq ft.
It’s a renovation. So complete gut.
It’s lighting and power for us. A basic office space.
The GC is saying he needs about 2 months per phase.
My work is about 3 men for 2 weeks each floor, so 4 weeks for a phase.
I don’t see how we would have men there for the entire duration of every phase?
Wouldn’t we maybe demo/disconnect, leave then come back and rough then install fixtures?
Looking at a job that has 9 phases
Each phase has work on two floors.
The overall job schedule is 3 years.
The area of work on each floor is about 2k sq ft.
It’s a renovation. So complete gut.
It’s lighting and power for us. A basic office space.
The GC is saying he needs about 2 months per phase.
My work is about 3 men for 2 weeks each floor, so 4 weeks for a phase.
I don’t see how we would have men there for the entire duration of every phase?
Wouldn’t we maybe demo/disconnect, leave then come back and rough then install fixtures?