Re: tops on feeders {service}
Hey, it must be the sinus drugs I'm on, becuase it makes sense to me.
I translate it as:
[I have a] 300A service [fed by] 350kcmil underground conductors. I want to tap these conductors with two sets of 1/0 and feed to two 150 amp main disconnects. [Each] disconnect will feed a transfer switch and [I will] use the existing panels as sub[panels]. Do you guys see anything wrong with this.