Im bidding a job and I have someone who is going to bring out their trencher and trench 250'. He'll give me a price for that but he doesn't backfill. Anyone have a labor rate I can use to figure how long its going to take to backfill 250' of 18" deep trench. Best guess is 5 hours but I honestly have no idea. Residential if it matters. Trench is from house to boat dock.
Thanks
Thanks