I took a few extra minutes to document this one today. Before we play spot the violations, it is accepted practice to forgo the romex connectors at the panel in cases where the come from in the wall.
House was built in about 1960 with a 3 phase delta service (for the AC) New AC is single phase so new service is single phase.
Before. POCO disconnected at 7:30 AM
Demo old stuff.
Nice washers on the toggle bolts.
Check cables for mythical bundling damage. Pristine as usual.
Needed bracing for the riser. Difficult in houses built like this. Flat 2x12 roof. POCo requires thru bolts thru framing members. Removed some trim, cut a hand hole and bolted on a couple of minnies. Used 2 1/2" IMC to get the required attachment height without back bracing.
Installed riser and hung new panel, top down.
Terminate conductors. Used the sim pull wire for the first time on the service conductors. Not good in this application. It felt like it had been sprayed with silicone and was hard to hold onto.
All done @ 5PM. Pulled new AC conductors thru existing conduit. PVC under panel contains the GEC and gas bond. Water bond is seperate/exposed.
If you look closely you will see that I had to go above and beyond and reroute a 1/2 copper water pipe that was in my way.
House was built in about 1960 with a 3 phase delta service (for the AC) New AC is single phase so new service is single phase.
Before. POCO disconnected at 7:30 AM
Demo old stuff.
Nice washers on the toggle bolts.
Check cables for mythical bundling damage. Pristine as usual.
Needed bracing for the riser. Difficult in houses built like this. Flat 2x12 roof. POCo requires thru bolts thru framing members. Removed some trim, cut a hand hole and bolted on a couple of minnies. Used 2 1/2" IMC to get the required attachment height without back bracing.
Installed riser and hung new panel, top down.
Terminate conductors. Used the sim pull wire for the first time on the service conductors. Not good in this application. It felt like it had been sprayed with silicone and was hard to hold onto.
All done @ 5PM. Pulled new AC conductors thru existing conduit. PVC under panel contains the GEC and gas bond. Water bond is seperate/exposed.
If you look closely you will see that I had to go above and beyond and reroute a 1/2 copper water pipe that was in my way.