Re: Uncooperative AHJ or Inspectors
Charlie B: I guess i don't understand your disagreement. I was trying to point out the difference in the language used to fail a job. The inspector cannot demand a change in design, but he can say that the design will fail as installed.
In a situation where a design calls for a lesser rated wire than the code requires, and the inspector calls it, that call can be looked at from several points of view.
I assume that you have no problem with the inspector waiting until the job was completed to fail it, wasting both the time and materials and labor to change it. I assume that you agree because any of the following statements made by an inspector could be construed as requiring a design change: "the number 14 wire needs to be #12."; "the #14 wire needs to be #12 to pass and if you change it, i will accept it."; "the code calls for #12 wire in this situation and i won't accept #14 wire".
I worked on a gov't job for a bit and the contractor was trying to do complex rewiring with carpenters from the Western Pacific. it was a minority contract and a rush job at the same time. We were told to work it out for the most part, but whenever it was out of their pocket, they complained that i was telling them what to do, de facto design, every time i did the up to code dance. So my boss told me to start failing them later in the process. they finally sub-contracted with real electrical and HVAC contractors. cost them most of their once large profit margin.
And it was all based on the ambiguity of how and when you say that it is not up to code.
And i didn't say that it was okay for an inspector to make designchanges.
paul
Charlie B: I guess i don't understand your disagreement. I was trying to point out the difference in the language used to fail a job. The inspector cannot demand a change in design, but he can say that the design will fail as installed.
In a situation where a design calls for a lesser rated wire than the code requires, and the inspector calls it, that call can be looked at from several points of view.
I assume that you have no problem with the inspector waiting until the job was completed to fail it, wasting both the time and materials and labor to change it. I assume that you agree because any of the following statements made by an inspector could be construed as requiring a design change: "the number 14 wire needs to be #12."; "the #14 wire needs to be #12 to pass and if you change it, i will accept it."; "the code calls for #12 wire in this situation and i won't accept #14 wire".
I worked on a gov't job for a bit and the contractor was trying to do complex rewiring with carpenters from the Western Pacific. it was a minority contract and a rush job at the same time. We were told to work it out for the most part, but whenever it was out of their pocket, they complained that i was telling them what to do, de facto design, every time i did the up to code dance. So my boss told me to start failing them later in the process. they finally sub-contracted with real electrical and HVAC contractors. cost them most of their once large profit margin.
And it was all based on the ambiguity of how and when you say that it is not up to code.
And i didn't say that it was okay for an inspector to make designchanges.
paul