I have a situation where the meter for a service in on the utility's pole and the SE conductors will be buried in a trench to the single family residence. Can the SE conductors enter the house below grade? (depth compliant with Table 300.5) The basement through 2nd floor wall is an insulated concrete form wall. A piece of Schedule 80 PVC (the SE raceway) will be placed in the wall before the concrete is poured. The PVC will be sealed as required by 300.5 (G). Is there a violation that I'm not seeing?