Mkinney
Member
- Location
- North Dakota
I have a unique situation here in North Dakota I would like you all to weigh in on. I have a 480 V service feeding a number of disconnects. The meter socket provided by the utility has a busbar installed to work as the main bonding jumper. I am being told i need to provide an additional grounded conductor to the main service disconnect located downstream and place the main bonding jumper in that location. There are two reasons I do not wish to do so. 1. If I place the main bonding jumper in that location I now need to remove the connection within the meter socket shown in the photo. Secondly as I have no use for the grounded conductor ( I am not using any 277 Loads) I believe this ruling to be in Error. If in fact I do provide the additional conductor I now have to isolate the grounded conductor within the meter enclosure to avoid a second bond. Has anyone else run into this?