bhluchan
Member
- Location
- Goshen, NY
- Occupation
- Electrical Engineer
I have a job where the contractors incorrectly installed the UPS and sprinkler pipe such that the piping run directly overhead of the UPS. What is everyone's opinion on whether this violates NEC 110.26(E) for Dedicated Equipment Space? The section specifically calls out 'switchboards, switchgear, panelboards, and motor control centers'.