Question for you utility folks, and possibly solar folks,
Is there anything special to net metering commercial solar? Are the actual CT's different size or type?
Are the meter jaws different? Anything ?
I was asked look into this for a church.
They have a proposed roof top solar project lined up 30kVA, and there is a July deadline now.
they have what appears to be an existing service of 400-500A at 208V 3ph,
pole bank of three cans then service is underground from pole.
Switch gear in in church basement has 5 main breakers and a CT metering section below, probably 1970's era.
This particular utility is very large possibly thru mergers and buy outs and has massive territory in several states they appear to have a unified standard for CT metering, that this churches CT meter setup does not meet, but it did meet at one time.
There was no issue with the Church and the utility prior to the request for solar net metering, and since the Church's demand usage is very low the utility does not need to upgrade a transformer or do anything other than install a NET meter.
The utility wants the CT's brought up to current standard, which involves moving the location of the Meter, and since the CT's have to be close to the meter (like within a foot) its no small task and the cost will kill the project.
I have ran into this beofre when CT's were on a pole and the utility did not want metering on their pole, but I am curious if there is a technical or life safety reason to upgrade the CT's or is this just red tape?
thanks
Is there anything special to net metering commercial solar? Are the actual CT's different size or type?
Are the meter jaws different? Anything ?
I was asked look into this for a church.
They have a proposed roof top solar project lined up 30kVA, and there is a July deadline now.
they have what appears to be an existing service of 400-500A at 208V 3ph,
pole bank of three cans then service is underground from pole.
Switch gear in in church basement has 5 main breakers and a CT metering section below, probably 1970's era.
This particular utility is very large possibly thru mergers and buy outs and has massive territory in several states they appear to have a unified standard for CT metering, that this churches CT meter setup does not meet, but it did meet at one time.
There was no issue with the Church and the utility prior to the request for solar net metering, and since the Church's demand usage is very low the utility does not need to upgrade a transformer or do anything other than install a NET meter.
The utility wants the CT's brought up to current standard, which involves moving the location of the Meter, and since the CT's have to be close to the meter (like within a foot) its no small task and the cost will kill the project.
I have ran into this beofre when CT's were on a pole and the utility did not want metering on their pole, but I am curious if there is a technical or life safety reason to upgrade the CT's or is this just red tape?
thanks
Last edited:
