woodturner9
Member
- Location
- Pennsylvania
The following question arose on another board, and I'm interested in hearing the experience and understanding of the folks on this board.
When I have upgraded or installed new residential service entrances, the utility has insisted that they specify the bonding location and ground configuration, and refused to connect if the install did not comply with their "rules". Usually the bond point has been the panel, but not always (I have installed service entrances in different states, municipalities, and for different utilities). In my experience, the utility has been adamant that it be done "their way" - to the point that, in one case, the utility's engineer advised me to do it "their way", get it inspected and connected, then change it to comply with NEC.
Another poster who is active on both this board and the other says that NEC dictates the bond point and essentially that what the utility says does not matter.
My question: what is your understanding and interpretation? How do you do it?
Thanks.
When I have upgraded or installed new residential service entrances, the utility has insisted that they specify the bonding location and ground configuration, and refused to connect if the install did not comply with their "rules". Usually the bond point has been the panel, but not always (I have installed service entrances in different states, municipalities, and for different utilities). In my experience, the utility has been adamant that it be done "their way" - to the point that, in one case, the utility's engineer advised me to do it "their way", get it inspected and connected, then change it to comply with NEC.
Another poster who is active on both this board and the other says that NEC dictates the bond point and essentially that what the utility says does not matter.
My question: what is your understanding and interpretation? How do you do it?
Thanks.