Currently I have the following electrical power layout for an airport project.
The utility company is providing a 75 kva transformer 13.8kV-120/240V single phase to power the airport. Since the transformer is too far away from this remote building we need to power, I am using a 75 kVA 240V - 2400V step up transformer to accomodate the voltage drop. Then i plan to have a 75 kVA 2400V-120/240V pad mounted step down transformer located outside the building. This will feed the building's main distribution panel. Now, there is a 0.58% voltage drop from the secondary side of the utility transformer to the step up transformer, there is a 1.97% voltage drop from the secondary side of the step up transformer to the primary side of the step down transformer, and there is a 0.58% voltage drop from the secondary side of the step down transformer to the main distribution panel inside the building. This is a total voltage drop of 3.13%. Does this mean that the branch circuits of the main distribution panel should not exceed (5% - 3.13% = 1.87%) in order to meet the NEC code. Does anyone have any suggestions or alternatives. Since i'm using all these transformers is there anyway around that 5% total voltage drop for main feeders and branch circuits?
The utility company is providing a 75 kva transformer 13.8kV-120/240V single phase to power the airport. Since the transformer is too far away from this remote building we need to power, I am using a 75 kVA 240V - 2400V step up transformer to accomodate the voltage drop. Then i plan to have a 75 kVA 2400V-120/240V pad mounted step down transformer located outside the building. This will feed the building's main distribution panel. Now, there is a 0.58% voltage drop from the secondary side of the utility transformer to the step up transformer, there is a 1.97% voltage drop from the secondary side of the step up transformer to the primary side of the step down transformer, and there is a 0.58% voltage drop from the secondary side of the step down transformer to the main distribution panel inside the building. This is a total voltage drop of 3.13%. Does this mean that the branch circuits of the main distribution panel should not exceed (5% - 3.13% = 1.87%) in order to meet the NEC code. Does anyone have any suggestions or alternatives. Since i'm using all these transformers is there anyway around that 5% total voltage drop for main feeders and branch circuits?
