We did a job almost a year ago so its technically still under warranty. The project was a fuel/gas station. The project was delivered on schedule and everything working no issues since completed. Fast-forward 10 months The customer is having some added equipment in the fuel pad area. The EC tried removing the existing wiring so they could add some new wiring to conduit but the wiring would not budge. Upon further investigation it was determined that we the original EC, us, mistakenly, accidentally, but not neglect some of the compound got past the packing and got poured into conduit causing a blockage where wiring couldn't be removed or added. There was nothing wrong with installation until the new wiring needed to be added. We arent trying to get with anything I just have a different point of view that my PMs and Boss. We are in process of repairing at own/EC expense but would you as a contractor how would you handle a situation with customer and employees. This wasnt done on purpose its just something that happened.