Quoted a job today to add a sub panel in a maintenance closet.  The house was built about a year ago or so.  While looking everything over I noticed that copper plumbing was run throughout the house and it exits the foundation in the maintenance closet and feeds everything from there.  I traced the ground for this pipe back to the ufer that comes up in the garage.  There’s also a #4 copper that runs from the ufer through the foundation and out to the service where bonding is done.  Was this done correctly? I haven’t seen it done like that before.  When copper plumbing is used, I normally run a #4 copper all the way back to the service and bond it there.
	
		
			
		
		
	
				
			 
				
 
 
		