bullheimer
Senior Member
- Location
- WA
last bid i was lowest bidder. i had contractors calling asking if i knew i was less than half of the bids they got already. (i still didn't get it cause the winner was the buddy of the gen)
this time i was at 130K and the lowest bids were 82 and 90K by UNION contractors. my material costs were 62K alone. a 4 story ware house 100% 3/4" rigid pipe and waterproof everything. i saw 644 hours because there was another 1 story 3000sq ft building and about 15 parking lot lights on 30 & 40 ft poles. at $75/hr for a jman ( my shop rate) and $20 for a helper times 644 it was about 60K for labor.
if you deduct just the COST of 62K from the 82K bid, you get 20K. at 50/hr that is 400 hours.
okay enuf griping, anybody know if a ibew contractor can bid labor at 50/hr? should i NOT be bidding my labor at 75/hr? the low bid i put in was a rigid job i bid at 75/hr as well. i was on the higher end of all the bids this time. i used a friends high dollar program (just for labor on installing rigid, NOT for the whole job) and it says 3.5 hours to run every ten feet of rigid from a light to a switch on cement. seems way too long, but if you figure in threading and screwing it together, drilling cement for anchors, measuring where your going to keep everything square, it doesnt seem that terribly out of whack does it? i guess if i would have bid it at one hour for a ten ft stick i would be closer to the 400 mark, but still, at that price, they would have made ZERO markup on material!! thats not right is it??? sign me, a sign of the times i guess
this time i was at 130K and the lowest bids were 82 and 90K by UNION contractors. my material costs were 62K alone. a 4 story ware house 100% 3/4" rigid pipe and waterproof everything. i saw 644 hours because there was another 1 story 3000sq ft building and about 15 parking lot lights on 30 & 40 ft poles. at $75/hr for a jman ( my shop rate) and $20 for a helper times 644 it was about 60K for labor.
if you deduct just the COST of 62K from the 82K bid, you get 20K. at 50/hr that is 400 hours.
okay enuf griping, anybody know if a ibew contractor can bid labor at 50/hr? should i NOT be bidding my labor at 75/hr? the low bid i put in was a rigid job i bid at 75/hr as well. i was on the higher end of all the bids this time. i used a friends high dollar program (just for labor on installing rigid, NOT for the whole job) and it says 3.5 hours to run every ten feet of rigid from a light to a switch on cement. seems way too long, but if you figure in threading and screwing it together, drilling cement for anchors, measuring where your going to keep everything square, it doesnt seem that terribly out of whack does it? i guess if i would have bid it at one hour for a ten ft stick i would be closer to the 400 mark, but still, at that price, they would have made ZERO markup on material!! thats not right is it??? sign me, a sign of the times i guess
Last edited by a moderator: