Hi. I have a situation at work. Where we have a DC UPS battery bank, being fed from a converter/inverter ATS, that is a parallel feed to a fused disconnect and then to the battery bank. We used Chase nipples and cable tray. I was told that the cable tray is a raceway. But art 392.2 defines it as a support structure and that the chase nipples is also a raceway but according to the UL-514B it’s a fitting. The real question is do we run 2 equipment grounding conductor? Which according to 250.120 (F)(1)(A) says I don’t. I’m saying I don’t need to. But yet I’m told I have to… nothing in the specs say. Im
Asking this to learn. Thank you.
Asking this to learn. Thank you.