jaylectricity
Senior Member
- Location
- Massachusetts
- Occupation
- licensed journeyman electrician
Doing a rehab on a house where most of the work is old-work. Thanks to the plumber (no really, I'm glad he needed some walls opened up) there are a few open sections of walls and the floor of the upstairs bathroom.
So I ran a bunch of wires, made up the boxes on the open walls, made the box-shaped cut on some of the existing walls, and poked wires through a hole in the wall in other locations. I even installed some of the old-work boxes and made them up so I could give a couple of switches for some temporary lighting.
The inspector comes for the rough inspection and calls me right away. Says I need to have all the old-work boxes in with the grounds and splices made up for the inspection.
I say, "I could have made them up, installed devices and plates and you wouldn't be able to inspect that anyway." Then he says, "Well if you can, you're supposed to install new-work recessed lights." Which I normally agree with, but in this case, a new work can wouldn't be able to be extended far enough down, so I figured it would be better to just have the sheetrocker cover the ceiling with 3/8ths as planned, then cut them out afterward. I had cut open the bay for each light location. We're talking strapping, wood lathe, steel mesh and plaster that was at least an inch thick altogether.
So he says, "The code doesn't say 'do it this way unless it's really hard'". Again, I agree, I could have cut the bays open further, installed enough wood to install a new work can sit flush after the 3/8ths sheetrock. But, come on.
The whole time, I was respectful about it. I said things like, "I understand where you're coming from, but look at what I'm working with there." I didn't say, but should have, "You can see how I make up my new work boxes, and you can even see how I plan to install my old-work boxes, do you think I'm going to do something different for the wires hanging out of holes in the wall?"
I did say, "All I want to know is if they can close up those walls. You can come back and look at the other stuff if you want to." He says, "They can close up the walls." Then he hung up on me. And also he signed the card for the rough.
So that's the backstory that leads to my question. What is the definition of a rough inspection? I always thought it was to inspect the wiring of the open walls to clear them to be insulated and sheetrocked.
What do you guys think?
So I ran a bunch of wires, made up the boxes on the open walls, made the box-shaped cut on some of the existing walls, and poked wires through a hole in the wall in other locations. I even installed some of the old-work boxes and made them up so I could give a couple of switches for some temporary lighting.
The inspector comes for the rough inspection and calls me right away. Says I need to have all the old-work boxes in with the grounds and splices made up for the inspection.
I say, "I could have made them up, installed devices and plates and you wouldn't be able to inspect that anyway." Then he says, "Well if you can, you're supposed to install new-work recessed lights." Which I normally agree with, but in this case, a new work can wouldn't be able to be extended far enough down, so I figured it would be better to just have the sheetrocker cover the ceiling with 3/8ths as planned, then cut them out afterward. I had cut open the bay for each light location. We're talking strapping, wood lathe, steel mesh and plaster that was at least an inch thick altogether.
So he says, "The code doesn't say 'do it this way unless it's really hard'". Again, I agree, I could have cut the bays open further, installed enough wood to install a new work can sit flush after the 3/8ths sheetrock. But, come on.
The whole time, I was respectful about it. I said things like, "I understand where you're coming from, but look at what I'm working with there." I didn't say, but should have, "You can see how I make up my new work boxes, and you can even see how I plan to install my old-work boxes, do you think I'm going to do something different for the wires hanging out of holes in the wall?"
I did say, "All I want to know is if they can close up those walls. You can come back and look at the other stuff if you want to." He says, "They can close up the walls." Then he hung up on me. And also he signed the card for the rough.
So that's the backstory that leads to my question. What is the definition of a rough inspection? I always thought it was to inspect the wiring of the open walls to clear them to be insulated and sheetrocked.
What do you guys think?