No, not at all. Only 2 motors will be added to this panelboard potentially: a 200hp motor and a 20hp motor. The other (2) motors are going in a different area of the facility and will not be connected at all to the 800a existing panelboard. In my OP, I suggested that we will be building a new service due to the lack of available power in that area.
If this second service is in a different area of same building as the original service you will have issues with multiple services to a building, better read up on art 230 part I before going ahead with this and maybe even get blessing from AHJ if you still want to go with it.