SolarBerger
Member
- Location
- Bishop, CA
- Occupation
- C-10 Electrical Contractor
I have an installation where I removed the main breaker from a 200A residential meter panel. I then ran conductors from the L1 and L2 busses that were connected to the line side of the main breaker. I used compression rings to terminate to the busswork with a belleville washer and the same size screw that connected the breaker to the buss. These connections were torqued based on the size of the bolt. These conductors land on a new main breaker in an ESS panel. The ESS panel is adjecent to the meter panel. From the ESS panel I then ran my L1 and L2 conductors back to the meter panel where i connected the conductors to the busswork that feeds the panels distribution or what was the main breaker load side connections. I used the same techniques of connection as the line side. Does this void the UL listing requirement for the meter panel? If so, can it be recertified as meeting the requirements?
Link to pic
Link to pic