Gliderboy100
New member
- Location
- Cumming, Ga. Forsyth
I have read the nec concerning the landing of the equipment ground. Is it permitted to land all of the leads, equipment grounding and neutral leads, to the neutral(grounding) bar in the panel. The panel being used is equipped with a main disconnect breaker making it, according to the panel manufacturer, a service equipment panel. The note in the panel indicates that the neutral(grounding) bar may be used if more space for equipment grounding conductors is required. I realize that the final answer is provided by the AHJ.
Correct or not?
Correct or not?