Hello,
I have a question regarding electrical panel load balancing.
Say you're doing a panel schedule and youre balancing the loads to get same wattage on each phase and your panel schedule ends up perfectly balanced with 10kW phase A, 10kW phase B, 10kW phase C. My question is why balance loads so perfectly on paper if we don't actually know which loads will be turned on at the site?
For example in the morning the building might have 4 kW worth turned on in phase A, 8kW on phase B and then 1kW on phase C.
In the afternoon it might change again say 9kW phase A, 2kW phase B and then 6kW phase C.
I feel like the panel will be always unbalanced despite having it balanced on ''paper'' because we dont know how the building will use their loads.
I hope my question makes sense..
Thank you!
I have a question regarding electrical panel load balancing.
Say you're doing a panel schedule and youre balancing the loads to get same wattage on each phase and your panel schedule ends up perfectly balanced with 10kW phase A, 10kW phase B, 10kW phase C. My question is why balance loads so perfectly on paper if we don't actually know which loads will be turned on at the site?
For example in the morning the building might have 4 kW worth turned on in phase A, 8kW on phase B and then 1kW on phase C.
In the afternoon it might change again say 9kW phase A, 2kW phase B and then 6kW phase C.
I feel like the panel will be always unbalanced despite having it balanced on ''paper'' because we dont know how the building will use their loads.
I hope my question makes sense..
Thank you!