Electrical Geek
Lead PV Service Electrician
- Location
- Massachusetts
- Occupation
- Electrician
My roofers (AKA apprentices) love doing this. When I can get them to go to the rail first, is a miracle. My question is when they bring the bond wire to the rail straight out of the junction box, they will take the cables that come out and, instead of going to the rail, they will go to the bond wire and tywrap them to it up to the rail above the box. I can't find anything in the code book that says that they can't do this. Where would I find it?