The withstand/short circuit rating for the switchboard is only 3 cycles based on UL 891.
If I have a time delay in the main circuit breaker more than 3 cycles to coordinate with the downstream circuit breakers, do I have to go with the switchgear, which will have 30 cycles withstnad rating per ANSI standard?