Not sure if this is the right place to post this.
We have some almost new construction, about 2 years old, and the contractors obviously didn't deburr any of the RMC. We have had multiple shorts in the RMC, pull new wire in and it lasts a few months, shorts again. It is in concrete thru mutiple floors (industrial) from 100' to 250' runs. Does anyone make something that we could pull thru to deburr?
We have some almost new construction, about 2 years old, and the contractors obviously didn't deburr any of the RMC. We have had multiple shorts in the RMC, pull new wire in and it lasts a few months, shorts again. It is in concrete thru mutiple floors (industrial) from 100' to 250' runs. Does anyone make something that we could pull thru to deburr?