Pulling a total of 45 CAT6 runs. 35 are 200' 10 are 100' lengths are approximate The drops are spread out in a wide pattern. 2 concentrated drops with 5-6 each, but none in the exact same spot
Install a Single main trunk with 40 j hooks then cable ties to structure from there (no, not a certified or EIA spec job)
Building is 175' x 175' there are many interior partitions that are framed, but its not tight.
Open bar joist ceiling 16-18' to the bottom of the bar joist. It is a very active construction site all trades working concurrently,
All the above are guesses based on 3rd party suppositions, you can't see the site before you start.
Assume two men, one lift, 8 hours a day, 8 1000' boxes of cable. Only the lift will remain overnight, all tools and materials must go.
How many days would you plan on?
I said 3 to be safe, thinking it would be 2. I get a note saying its 24 man hours allowed. I guess you could hack it in without hooks and zip tie nothing and still not be done
Install a Single main trunk with 40 j hooks then cable ties to structure from there (no, not a certified or EIA spec job)
Building is 175' x 175' there are many interior partitions that are framed, but its not tight.
Open bar joist ceiling 16-18' to the bottom of the bar joist. It is a very active construction site all trades working concurrently,
All the above are guesses based on 3rd party suppositions, you can't see the site before you start.
Assume two men, one lift, 8 hours a day, 8 1000' boxes of cable. Only the lift will remain overnight, all tools and materials must go.
How many days would you plan on?
I said 3 to be safe, thinking it would be 2. I get a note saying its 24 man hours allowed. I guess you could hack it in without hooks and zip tie nothing and still not be done