Can you run a continuous GEC run from water meter to meter socket then to ground rod? I recently had to do this when an ice storm hit a while back. The panel I was working on was an old 60 amp fused panel with no room what so ever to bond the GEC. So I decided to do what I mentioned above, per local AHJ requiring us to bring grounding and bonding up to code if we changed the meter socket to a 200 amp by-pass meter socket.
The city inspector saw this and he said that he had never seen it ran like that before, although he did not have a problem with it. I was just curious what someone else thinks.