Power house electrical distribution for chillers, cooling towers, boilers, and compressors. Also in the 1st picture is a couple replaced capacitor bank disconnects and their feeders. Any gear breakers that were not serviced over partial shutdowns in '14 holidays are completed now.
View attachment 12301
View attachment 12302
The team, some will have 20+ hours today.
Behind that wall is our S&C H.V. distribution, (23900v.). Two POCO feeders in, our A/B feeders out, (feeding 4 double ended sub stations and 1 single), and feeds to 4160v. and 480v. transformers for the power house distribution shown above. Service here is what demanded a total outage. Arc barriers & cleaning.
View attachment 12303
View attachment 12304
Both sides pictured, tie at far right, (of rt. pic.)
Behind that gear, an acre or so donated to the POCO was traded for a more direct line from the generating station. We no longer loose service if a branch falls on a line in a nearby neighborhood. A similar deal with the county Fire department was done at the front. This means a firetruck or ambulance can reach us from their back door fast!
View attachment 12305
View attachment 12306
Powering was beginning as I had to leave.
Hated to leave, but a new policy will not allow me more than 12 hrs. I didn't apply to the E.E. or our contractors. They still had to leave a substation down to land the new bus feeders. Hopefully they are getting out of there about now, coming up on 24 hrs. for most of them.