42P panel all with 1P 20A breakers(all #10 wire) and separate neutrals. Say there are about 7 homeruns with 6 circuits each.....all said and done with grounds there are about so about 91 #10 wires. So NECA and what we have used in the past is roughly about 5 minutes per wire. This includes dressing, tagging/labeling and terminations. So this is about 7-8 hours for all 91 wires. I know there are variables such as doing them all at once or going back and forth.
Does 7-8 hours(basically one day) seem reasonable to you guys?