emt hours

Status
Not open for further replies.

normbac

Senior Member
need to estimate time to run 9 230ft rows of 1/2 inch emt with j box every 40ft it will be 30ft up hung on steel truss any guess on hours for two guys to do this? TIA :-? :-?
 

hardworkingstiff

Senior Member
Location
Wilmington, NC
Is the ground clear? Shelving, desks, etc need to be moved? One lift or two? Foot traffic to worry about (having to secure a work area)? Any customer requirements that may slow things down?
 

normbac

Senior Member
open warehouse no obstructions not moved in yet one lift
4s boxes caddy clips or possibly down the v shape and strap some how?
 

hardworkingstiff

Senior Member
Location
Wilmington, NC
My guess would be

1st day show up, get set up and get system going, probably get 25% completed. 2nd day, zip along and wonder why you didn't get more done yesterday. Come close, but not quite finish.

3rd day, clean up, clear out, milk a whole days work out of this.
 
Status
Not open for further replies.
Top