Imo, if you do a panel change then you are responsible for labeling the panel. If you added a circuit to an unlabeled panel then, IMO you only need to label the circuit you worked on. I agree with Trevor--- 408.4 says it all.
Michael, I bet you knew I was going to say that....hahaha
Michael, I bet you knew I was going to say that....hahaha