We have a CT cabinet that feeds a 400 amp ATS and the ATS feeds a manual transfer switch. The manual switch then feeds the 200 amp panels. Question is where do the ground and neutrals bond together? Typically it the first panel after the meter but in this case, the CT cabinet doesn't have a breaker neither does the ATS. As of now the ground are separated in the ATS and at the MTS. Originally the CT cabinet fed the MTS and a ATS was added and then it fed the MTS. The MTS was left so if the generator had an issue, the MTS could be operated. It's at a diary and that's the main reason the MTS was left in place. Just not sure where the neutrals and ground need to be bonded together.