I am having some electrical work performed in a newly rebuilt section of building. This room will have its own 3 phase 200A sub panel fed from the service entrance panel elsewhere in the building. A 200A ATS is located adjacent to the panel for a voluntarily equipped standby power generator. My question is regarding the mounting location of the transfer switch and panelboard. The panelboard is situated on a wall which has a ledge about 5 feet high and 24" deep. I would like for the panel to be located on the section of wall above this ledge. The panel will be mounted so that the uppermost breaker is no more than 6'7" from the floor. However, my electrican believes that the wall "bump out" under the panel violates the space requirements around the equipment. This section of wall is the only place in the room where the equipment can be surface mounted and available for additional wiring connections (which are extremely likely) once the room is finished. Can anyone make reccomendations for mounting the panel and ATS in this situation? See this picture for details: