1.) 225.31 says all ungrounded conductors that supply or pass thought the building or structure needs to have disconnection means.
Q: If the "structure" is a pool panel and is indeed a structure would it require disconnection means at the panel for the pool to disconnect the ungrounded feeders per the NEC.
Q: The 6 disconnect or 6 throw allowance would not play a part in this....would it ?
In other words, can they use a MLO panel with no disconnection means ont he feeders to this "structure".
I say they need to still have disconnection means at the pool panel to disconnect all ungrounded conductors that supply this panel.
Thanks in advance
1.) 225.31 says all ungrounded conductors that supply or pass thought the building or structure needs to have disconnection means.
Q: If the "structure" is a pool panel and is indeed a structure would it require disconnection means at the panel for the pool to disconnect the ungrounded feeders per the NEC.
Q: The 6 disconnect or 6 throw allowance would not play a part in this....would it ?
In other words, can they use a MLO panel with no disconnection means ont he feeders to this "structure".
I say they need to still have disconnection means at the pool panel to disconnect all ungrounded conductors that supply this panel.
Thanks in advance