Same installation scenario. 3/4" EMT vs. 3/4" RGS all in on both...support, connector, cut & thread(RGS). Was told that the labor is at least double for the RGS...exactly what I was told is below
So if you have 50' run on EMT and it's 5 hours.... the RGS will take about 12-13. I know the cutting and threading is time consuming.
Agree?
So if you have 50' run on EMT and it's 5 hours.... the RGS will take about 12-13. I know the cutting and threading is time consuming.
Agree?