Stevenfyeager
Senior Member
- Location
- United States, Indiana
- Occupation
- electrical contractor
I am always doing residential single phase work. Sometimes I will run a new circuit for a store with 3 phase. That is as much as I have done. But this customer wants an estimate for a new 3 phase service in addition to their single phase service because they are adding two machines, both 60 amp, 208 v. The customer said that converters are too expensive for the machines to use the existing single phase service.
I've priced a 3 phase underground feed meter, 3 phase 200 amp panel, and breakers and disconnects. I still need to price the permit, the last time I worked for a store in this town, the permit was $400. I will be meeting with POCO Friday. Is there anything I need to know about my first new 3 phase install? Grounding, for example? (this is a pole barn type building) Any advice would be appreciated. Thank you very much!
I've priced a 3 phase underground feed meter, 3 phase 200 amp panel, and breakers and disconnects. I still need to price the permit, the last time I worked for a store in this town, the permit was $400. I will be meeting with POCO Friday. Is there anything I need to know about my first new 3 phase install? Grounding, for example? (this is a pole barn type building) Any advice would be appreciated. Thank you very much!