I am breaking ground on a two story shop building. It will have 400A service via a POCO pad mounted transformer 15 ft from the building. I plan two 200A panels in the shop. I also plan two 200A panels in an adjacent home that will be built in a year. I have seen discussions close to this but not quite. With my newbie experience, I see a couple of options:
1. Meter > 400A fused exterior disconnect > trough, then taps to the two shop 200A interior panels and an exterior tap about 60 feet or so to the home > trough > two 200A exterior disconnects > two interior 200 Panels.
2. Meter > trough > tap to two shop exterior disconnects and exterior tap to house..... (not sure about the disconnects being after the trough and taps though?)
3. Meter lugs x3 to 2 shop disconnects and ext tap to home..... ( not sure about this one either)
Once I get that settled, I'll look at ways to connect generator to the whole system if possible, and solar (not POCO backfeeding).
I'm learning every day and looking forward to your collective wisdom!
FYI, We are operating under 2023 NEC.
1. Meter > 400A fused exterior disconnect > trough, then taps to the two shop 200A interior panels and an exterior tap about 60 feet or so to the home > trough > two 200A exterior disconnects > two interior 200 Panels.
2. Meter > trough > tap to two shop exterior disconnects and exterior tap to house..... (not sure about the disconnects being after the trough and taps though?)
3. Meter lugs x3 to 2 shop disconnects and ext tap to home..... ( not sure about this one either)
Once I get that settled, I'll look at ways to connect generator to the whole system if possible, and solar (not POCO backfeeding).
I'm learning every day and looking forward to your collective wisdom!
FYI, We are operating under 2023 NEC.