electrician538
Member
The city inspector says that the Arlington 40AST ac cable connectors I used in patient care rooms must all be changed out to the set screw type. I just checked Arlingtons web sight and it says the 40AST connectors are for AC/HCF applications. Is this guy just making it tough on an out of town contractor or is this common?
He also doesn't like the bare bond wire in the cable to be wrapped back around the sheath and anywhere this was done must changed and cut off flush. We normally pipe all our hospital jobs in my home town and the ac cable is a little out of my element. Just wondering if this guy is in the norm in his requests.
He also doesn't like the bare bond wire in the cable to be wrapped back around the sheath and anywhere this was done must changed and cut off flush. We normally pipe all our hospital jobs in my home town and the ac cable is a little out of my element. Just wondering if this guy is in the norm in his requests.