BMacky
Senior Member
- Location
- Foster City, CA
Hi,
I am in the early stages of quoting numbers for installation of lighting in a 10,000 sf space. About 180 2 x 4 fluorescent troffer-style fixtures, 14 2 x 2s, and various exit and emergency lighting fixtures.
Anyone have a reasonably accurate labor unit for dropping 2 x4's in, attaching pre-hung support wires, clip onto the grid, and (these will come pre-bulbed) wiring to my guess would be an MC whip, and moving on to the next one?
Does 20 minutes seem too long? These are going to be palletized, shrink wrapped so we don't have to deal with the boxing issues. The space has 10-foot ceilings so we will be moving 8 foot step ladders along, or maybe a rolling scaffolding, in several office suites.
Suggestions? Guidance? Humor? Horror stories? Will accept all input.
Thanks!
Bob
I am in the early stages of quoting numbers for installation of lighting in a 10,000 sf space. About 180 2 x 4 fluorescent troffer-style fixtures, 14 2 x 2s, and various exit and emergency lighting fixtures.
Anyone have a reasonably accurate labor unit for dropping 2 x4's in, attaching pre-hung support wires, clip onto the grid, and (these will come pre-bulbed) wiring to my guess would be an MC whip, and moving on to the next one?
Does 20 minutes seem too long? These are going to be palletized, shrink wrapped so we don't have to deal with the boxing issues. The space has 10-foot ceilings so we will be moving 8 foot step ladders along, or maybe a rolling scaffolding, in several office suites.
Suggestions? Guidance? Humor? Horror stories? Will accept all input.
Thanks!
Bob