Hey guys. Just wanted to see where some of you would be on a project I bid today. Here are the particulars.
-remove and replace 8 parallel runs of 3x500mcm about 120' each
-remove and replace 8 parallel runs of 3x350mcm about 75' each
-remove and replace 1200A split buss switchboard with 4-600A breakers, electrically interlocked so only 2 breakers can be closed at any time, switchboard cost was about $21,000
-remove and replace control wiring for four generators that parallel with the utility, there are about 80 terminations, all #12, approx. 100' per run
-Davis -Bacon wage, package is about $77.00 an hour, and the job is out of town. Per Diem of $150 per day. Work has to be done in 1 week, I figure 4 guys.
That, in a basic description is the whole project. I think we got it but was told we left quite a bit on the table. Usually I'm high and trying to figure out, what did I miss?!
-remove and replace 8 parallel runs of 3x500mcm about 120' each
-remove and replace 8 parallel runs of 3x350mcm about 75' each
-remove and replace 1200A split buss switchboard with 4-600A breakers, electrically interlocked so only 2 breakers can be closed at any time, switchboard cost was about $21,000
-remove and replace control wiring for four generators that parallel with the utility, there are about 80 terminations, all #12, approx. 100' per run
-Davis -Bacon wage, package is about $77.00 an hour, and the job is out of town. Per Diem of $150 per day. Work has to be done in 1 week, I figure 4 guys.
That, in a basic description is the whole project. I think we got it but was told we left quite a bit on the table. Usually I'm high and trying to figure out, what did I miss?!