four sets of feeders pulled from gear to pullbox then to a mdp.all conduits have bond bushings. i landed the ground wire thru the bond bushing lugs at all points. the inspector says i should not have done this i should have let the ground go thru and put a jumper from all the bushings ay each point total of 4 conduits at 4 locations and pulled thru4 bushings and into a ground bar.
this would give me a bond at panel at gear and two in the pull box.
opinions THANKS