Changeover Fitting

Status
Not open for further replies.

hurk27

Senior Member
Now I got your question. Strip off the mc and then put the connector, coupling, connector. Some of the walls were over 16 feet tall and it was a major pia to strip off that much mc and then jam down the 1/2 emt. Like i posted earlier, I thought it was a crappy install.
Not my money, not my call.

An't no way, that had to be a job stripping that much MC, I would have used FMC, at least you would just pull the conductors in both the EMT and the FMC.
 

iwire

Moderator
Staff member
Location
Massachusetts
An't no way, that had to be a job stripping that much MC, I would have used FMC, at least you would just pull the conductors in both the EMT and the FMC.

We do this all the time, strip 20' 30' of MC and slid into the conduits.

It is very simple.
 
Status
Not open for further replies.
Top