Now I got your question. Strip off the mc and then put the connector, coupling, connector. Some of the walls were over 16 feet tall and it was a major pia to strip off that much mc and then jam down the 1/2 emt. Like i posted earlier, I thought it was a crappy install.
Not my money, not my call.

An't no way, that had to be a job stripping that much MC, I would have used FMC, at least you would just pull the conductors in both the EMT and the FMC.
 
An't no way, that had to be a job stripping that much MC, I would have used FMC, at least you would just pull the conductors in both the EMT and the FMC.

We do this all the time, strip 20' 30' of MC and slid into the conduits.

It is very simple.
 