We dont do a lot of commercial garage work so bear wtih me.We are wiring a car dealership that has a service workshop where they will be performing major repair as noted in 511.2.Looking @ 511.3 (c)(1) ventilation not provided-&511.3(c)(2) ventilation not provided-My question is,- do we need to install conduit seals when entering non-explosion proof equipment?ex:we want to install a 4" panel feeder undergrd. from the main elec.room to a panel in the service workshop area.(note:the panel already went thru the submittal process and was approved as a standard nema -1 tub)
And if we do need to install conduit seals they should be within the 18" as mentioned in 511.3 floor areas?As I mentioned we do not do alot of this work,and we want to do the correct installs,any help would be appreciated,thanks