Hi everyone, I am running 3 feeder circuits underground from A to B and using a common EGC in the trench, the 3 circuit conductors will have a transition to a bottom entry equipment using PVC 90 sweeps (one PVC 90 per circuit), my question is how am I supposed to bring the EGC inside the equipment, can I just pull the common EGC into any one of the three conduits (violation of circuit conductors must run with EGC in the same raceway) or I need to make 3 taps off the common EGC into each conduit (each circuit conductors will have a separate EGC running in the same conduit). I am also thinking what if in a different scenario where I need to run 3 parallel conductors (only one circuit) underground and make the transition, how do I bring the common egc into the equipment to comply with 310.H.(3)
Thanks a lot for the help!
Thanks a lot for the help!
Last edited: