We've avoided the issue. Let's retreat a bit ...
I'll use a certain commercial job as an example. In that building, the gas immediately transitioned to CSST as soon as it entered the building. The CSST ran without splice or connection about 120-ft, up walls and across ceilings, until it arrived at the furnace. There were no other gas appliances on this line.
Now ... I consider the furnace 'end' to be bonded by way of the appliance, and the 3-prong code for the igniter. It's the rest of the run that has me confused.
Was I supposed to run a ground to the gas piping at the start of the run? Would a length of #12 to a nearby 4-square be enough? Could I just beam-clamp a jumper to the nearest I-beam? Or, do I need a #6, in pipe, all the way back to the service?
Likewise, am I expected to run a ground wire (what size?) along the length of the CSST, thus bonding the two sections of 'hard' pipe together?