AC\DC
Senior Member
- Location
- Florence,Oregon,Lane
- Occupation
- EC
Got in a rush and was trying to save customer money on parts back fired the old Myers hub was not the Bonding Myers hub and I have to correct that, since the Ridgid is not bonded properly. I don't want to get power company to kill her power and all and cause her a fuss. I was thinking of doing a Pierce connector on the neutral at service mast and install a 2" pipe clamp on the service mast to bond it any reason a pipe clamp won't work.