The entire decking is coming out and roof from ground floor is about 18’
The previous ct is under the ramp to the left don’t know how it was passed
The entire decking is coming out and roof from ground floor is about 18’
The previous ct is under the ramp to the left don’t know how it was passed
Yea, I've had that thought many times.Now I wondering if I did not charge enough lol.
IDK, 2020 NECA shows 2 inch PVC schedule 40 conduit at 8hr per 100ft. Another labor manual is showing between 3 and 4 the per 100ft and still another is giving .07hr per foot.He seemed happy with the bid. I though in laying the power company pipe its like 3 runs off 400 feet 2' pvc, but that won't take me longer than a couple hours. Thanks for the input. Now I wondering if I did not charge enough lol.
AC, not clear on this part, you didn't describe that in the OP. 3 400 foot runs? What size wire?It’s in a trench and going to glue up top and throw it in. Won’t take that long my estimate software said what your saying. It won’t take that long
If I was stap it to a wall or something like that then I would believe it.
Not that simple for running parallels, need to maintain specific spacing between the individual conduit runs. The one I did had to be 7.5 inch spacing see figure 310.60(C)(3).Don’t know power company’s deal , I just have to lay pipes. I originally did not have in price, so did not include in op. Unless I am missing something, I just lay it out and glue above ground and throw in, couple hrs.
That word never bit you before, right?I’ll check that again. I assumed since it power company side that would not apply. I’ll call power company and ask. I guess if so I’ll adjust my bid.
Do you realize 310.60 is for over 2kv?Not that simple for running parallels, need to maintain specific spacing between the individual conduit runs. The one I did had to be 7.5 inch spacing see figure 310.60(C)(3).
Missed that but thought I saw the same for a duct bank on lower voltage. Was looking at an electronic version and saw the layout. Found later the same measurement for 0 to 2000 in relation to table 310.15(B)(2)(7)Do you realize 310.60 is for over 2kv?