herding_cats
Senior Member
- Location
- Kansas
- Occupation
- Mechanical Engineer
I'm getting ready to tie in three (3) 200A subpanels from a large 3000A MDP. My question is are grounding bushings required on both ends of the EMT or just one? I'm running 2" EMT on all three subpanels. 208vac 3-phase. If I remember right I just need bushings on the subpanel side?